The following are:
2,000 6" blocks @130 =260,000
110 bags of cement. =198.000
For all job
Granite 15 tons, = 80,000
Sand for setting. = 35,000
Sand for rendering, = 30,000
Laterite 7trucks, =140,000
Rod 20lgn, = 30,000
Plank 25lgn, = 20.000
Roofing, &lab =400,000
Window sliding, &lab. = 85,000
P v c, and lab = 85,000
Doors, and lab =160,000
Tiles all, and lab =150,000
Sanitary and lab, = 85,000
Wiring and lab, =150,000
Labour on mason,capen,
Iron bendin,labourer, =370,000
Burglary, = 60,000
Soakaway , =100,000
I can supervise the job for you